DODDINGTON ROAD, EARLS BARTON

Client / Consultant: Kier Transportation
Start Date: September 2025
Duration: 1 Week
Location: Doddington Road, Earls Barton
Value: £11,248.00
Project Details:

Installation of a new road gully, connected up to existing highway drainage. Vacuum excavation was required due to the presence of underground services in the carriageway and adjacent footway.

The works were competed under 2-way traffic lights with traffic and pedestrian management undertaken by NC & JC Construction.

The works were completed for Kier Transportation under the North Northamptonshire Highways Term Maintenance Contract.