Ringway Jacobs
Project Details
Civils works to enable the replacement of a road bridge at Hulcote Mill, Central Bedfordshire.
Works include tree removal, excavation, assisting diversion of sewers, widening of access road, creation of a hard standing area and abutment ballast walls, surfacing works and foundations for temporary and permanent bridge.
Temporary and permanent bridge was supplied and installed by Retro Bridge with NC & JC overseeing the works.
Client / Consultant:
Start Date:
September 2021
Duration:
28 Weeks
Location:
Hulcote Mill, Central Bedfordshire
Value:
£367,000