Corby Borough Council / Sursham Tompkins & Partners
Project Details
Installation of concrete hardstanding approximtely 2600m2 in area to existing industrial unit.
Works consisted of 225mm reinforced concrete slab on Type 1. Existing surfacing crushed, mixed and used as capping. Drainage consisted of linear channel drains, cellular storage and Hydro braked outfall into existing storm water system.
Client / Consultant:
Start Date:
January 2018
Duration:
12 weeks
Location:
Corby, Northampton
Value:
334,000